Levelling Up Fund Round 2: Programme Delivery Plan

Funded by UK Government logo

Information about the Levelling Up Fund Round 2 project's programme delivery plans.

Delivery plan key milestones

All delivery plan milestones are provisional and are based on best information at this stage in the project’s development. 

This information will be updated if information changes.

Select one of the following projects to view it's delivery plan key milestones:

St Peter's Square
St Peter’s Square Programme Delivery Plan
Key Milestone Date 
Consultation and engagement Completed April 2024
Detailed designs available October 2024
Traffic Regulation Order submitted November/December 2024
Procurement start March 2025
Construction start September 2025
Handover February/March 2026
St Peter's Church and Cloisters
St Peter's Church and Cloisters Programme Delivery Plan
Key Milestone Date 
Procurement start October/November 2024
Construction start December 2024
Construction Finish / Handover December 2025
Ruthin Clock Tower
Ruthin Clock Tower Programme Delivery Plan
Key Milestone Date 
Procurement start Completed July 2024
Consultation and engagement Completed April/May 2024
Construction start August 2024
Construction finish / Handover November 2024
Ruthin Gaol/46 Clwyd Street
Ruthin Gaol/46 Clwyd Street Programme Delivery Plan
Key Milestone Date 
Detailed designs available Completed May 2024
Planning application submitted Submitted July 2024
Procurement start October 2024
Construction start December 2024
Construction finish / Handover March 2025
Ruthin Nantclwyd y Dre
Ruthin Nantclwyd y Dre Programme Delivery Plan
Key Milestone Date 
Planning application submitted Submitted August 2024
Procurement Start November 24
Construction start February 2025
Construction finish / Handover September 2025
Ruthin Cae Ddol
Ruthin Cae Ddol Programme Delivery Plan
Key Milestone Date 
Consultation and engagement Completed April/May 2024
Construction Start September 2025
Construction finish / Handover February/March 2026
Moel Famau Facilities and Cycle Paths
Moel Famau Facilities and Cycle Paths Programme Delivery Plan
Key Milestone Date 
Consultation and engagement Ongoing
Planning application submitted Submitted July 2024
Procurement start March 2025
Construction start May 2025
Construction finish / Handover December 2025
Loggerheads Building and External
Loggerheads Building and External Programme Delivery Plan
Key Milestone Date 
Consultation and engagement Ongoing
Planning Application and FRAP Consent App Submitted Submitted July 2024
Procurement start January/February 2025
Construction start April 2025
Construction finish / Handover September 2025
Bryneglwys School - Community Hub
Bryneglwys School - Community Hub Programme Delivery Plan
Key Milestone Date 
Procurement start Completed, Grantley Lowe Ltd awarded contracted
Construction start Started July 2024
Handover December 2024
Gwyddelwern - Community Hub
Gwyddelwern - Community Hub Programme Delivery Plan
Key Milestone Date 
Planning application Submitted Submitted August 2024
SAB application submission Submitted October 2024
Procurement start March 2025
Construction start July 2025
Construction finish / Handover April 2026