Levelling Up Fund Round 2: Programme Delivery Plan
Information about the Levelling Up Fund Round 2 project's programme delivery plans.
Delivery plan key milestones
All delivery plan milestones are provisional and are based on best information at this stage in the project’s development.
This information will be updated if information changes.
Select one of the following projects to view it's delivery plan key milestones:
St Peter's Square
St Peter’s Square Programme Delivery Plan
Key Milestone |
Date |
Consultation and engagement |
Completed April 2024 |
Detailed designs available |
October 2024 |
Traffic Regulation Order submitted |
November/December 2024 |
Procurement start |
March 2025 |
Construction start |
September 2025 |
Handover |
February/March 2026 |
St Peter's Church and Cloisters
St Peter's Church and Cloisters Programme Delivery Plan
Key Milestone |
Date |
Procurement start |
October/November 2024 |
Construction start |
December 2024 |
Construction Finish / Handover |
December 2025 |
Ruthin Clock Tower
Ruthin Clock Tower Programme Delivery Plan
Key Milestone |
Date |
Procurement start |
Completed July 2024 |
Consultation and engagement |
Completed April/May 2024 |
Construction start |
August 2024 |
Construction finish / Handover |
November 2024 |
Ruthin Gaol/46 Clwyd Street
Ruthin Gaol/46 Clwyd Street Programme Delivery Plan
Key Milestone |
Date |
Detailed designs available |
Completed May 2024 |
Planning application submitted |
Submitted July 2024 |
Procurement start |
October 2024 |
Construction start |
December 2024 |
Construction finish / Handover |
March 2025 |
Ruthin Nantclwyd y Dre
Ruthin Nantclwyd y Dre Programme Delivery Plan
Key Milestone |
Date |
Planning application submitted |
Submitted August 2024 |
Procurement Start |
November 24 |
Construction start |
February 2025 |
Construction finish / Handover |
September 2025 |
Ruthin Cae Ddol
Ruthin Cae Ddol Programme Delivery Plan
Key Milestone |
Date |
Consultation and engagement |
Completed April/May 2024 |
Construction Start |
September 2025 |
Construction finish / Handover |
February/March 2026 |
Moel Famau Facilities and Cycle Paths
Moel Famau Facilities and Cycle Paths Programme Delivery Plan
Key Milestone |
Date |
Consultation and engagement |
Ongoing |
Planning application submitted |
Submitted July 2024 |
Procurement start |
March 2025 |
Construction start |
May 2025 |
Construction finish / Handover |
December 2025 |
Loggerheads Building and External
Loggerheads Building and External Programme Delivery Plan
Key Milestone |
Date |
Consultation and engagement |
Ongoing |
Planning Application and FRAP Consent App Submitted |
Submitted July 2024 |
Procurement start |
January/February 2025 |
Construction start |
April 2025 |
Construction finish / Handover |
September 2025 |
Bryneglwys School - Community Hub
Bryneglwys School - Community Hub Programme Delivery Plan
Key Milestone |
Date |
Procurement start |
Completed, Grantley Lowe Ltd awarded contracted |
Construction start |
Started July 2024 |
Handover |
December 2024 |
Gwyddelwern - Community Hub
Gwyddelwern - Community Hub Programme Delivery Plan
Key Milestone |
Date |
Planning application Submitted |
Submitted August 2024 |
SAB application submission |
Submitted October 2024 |
Procurement start |
March 2025 |
Construction start |
July 2025 |
Construction finish / Handover |
April 2026 |